HOW TO COMPILE 100PCS HARDWARE IN 24HOURS? - Seeeduino Cloud

We did the experiments last month for our own project. Before the production, we hold the pre-meeting at 17:00, we fix the main timeline in the whole schedule. This time, we try to challenge a relatively complex product called Seeeduino Cloud, and we will record all the processes including PCB fabrication.

17:00 Pre-meeting

17:30 Release PO to PMC

17: 40 Run MRP

18:00 Preparing components in warehouse


18:30 Our PCB factory Start to produce PCB- Cut Lamination

Drilling


Plated through hole

Exposure




Developing

IMMERSION GOLD

Silk screen

Flying Probe test

Routing

PCB-Packaging

Ready to ship


The next morning~
8:30 PCB arrived to our MFG center& Our QC do incoming inspection


8:35 Put electronic components on feeders


9:00 Debug the Automatic Printer + Pick and place machine



9:10 QC check the components on Pick and place machine.


9:40 Make the first article


10:10 Components inspection

10:20 First article pass reflow



10:30 First article visual inspection


10:40 First article function test


11:00 Start SMT Production




12:00 Start Cell line Production



14:00 Testing

15:00 Failure analysis

15:30 FQC inspection


16:15 Packaging



16:30 Put in storage




In final, we completed the order in 24 hours, thanks all the guys in the team, thanks our project manager Eiki, she not only should ensure all the schedule on the right time, but also need to take all the photoes for sharing. If you want to get more information about 24 hours order service or want to try the service, you can apply it on our propagate page, seeedstudio.com/propagate/app/start, we will do the experiment and share every week.
















































thanks for the useful information and it was nice to know this